How to Handle Change Orders Without Losing Money

This guide is for general information. It is not legal advice. Contract rules vary by state and project, so have an attorney review your contract and change order forms.

“While you’re here, can you also…” It’s one of the most common phrases on any job site, and one of the most expensive. A few extra outlets, a different tile, moving a fixture six inches. Each change seems small, so it gets done with a handshake. At the end of the job, the extra work adds up to days of labor, the client remembers a different price and the profit is gone.

Change orders exist to prevent exactly that. A change order is a written agreement to change the scope, price or schedule of a job. Handled well, changes become additional profit. Handled poorly, they’re the biggest source of disputes and lost money in contracting.

This guide explains how to set up your contracts for changes, the step-by-step change order process, how to price changes correctly and how to deal with clients who want changes without paperwork.

Quick answer: handle change orders by including a change order clause in every contract, documenting each change in writing before doing the work, pricing it with labor, materials, overhead, profit and schedule impact, getting the client’s signature and billing for it on a clear schedule. Never do extra work on a verbal approval alone.

What a change order is

A change order is a written document that modifies the original contract. It typically changes:

  • Scope: adding, removing or modifying work.
  • Price: increasing or decreasing the contract amount.
  • Schedule: extending or adjusting the completion date.

Larger construction projects often use standard forms, such as those published by AIA Contract Documents. On federal projects, contract changes follow the rules in FAR Part 43. Small contractors can use a simple one-page form, as long as it captures the essentials.

Why contractors lose money on changes

  • Verbal approvals that clients later dispute.
  • No price agreed before the work is done.
  • Underpricing, by charging only materials and forgetting labor, overhead and profit.
  • Ignoring schedule impact, such as extra days on site or rescheduled trades.
  • Billing late, after the client has forgotten why the work was added.
  • Scope creep: many small favors that were never written down.

Types of change orders

Client-requested changes

The client wants something added, upgraded, moved or removed.

Unforeseen conditions

You discover something no one could see when the job was priced: rot behind a wall, outdated wiring, a cracked drain line, a code violation.

Design or code changes

An inspector requires additional work, or plans change after approval.

Each type should go through the same written process.

Step 1: Put a change order clause in every contract

Your estimate or contract should state:

  • All changes must be in writing and signed before the work is done.
  • How changes are priced, such as your hourly rate and material markup, or a fixed price per change.
  • How the schedule may be affected.
  • When change orders are paid, such as with the next progress payment or before work begins.
  • How unforeseen conditions are handled, including exclusions for hidden damage.

Setting expectations at the start makes later conversations easier. The FTC’s guide to hiring a contractor also encourages homeowners to get changes in writing, so a clear process protects both sides.

Step 2: The change order process

  1. Stop and identify the change. When a client asks for something new, or you discover an unforeseen condition, recognize it as a change before you start.
  2. Describe the change in plain language.
  3. Price it, including labor, materials, overhead, profit and schedule impact.
  4. Present it to the client in writing, with the price and any schedule change.
  5. Get a signature, on paper or electronically, before doing the work.
  6. Do the work.
  7. Bill for it according to your contract terms.

If the change is urgent, such as a burst pipe discovered mid-job, get at least a written approval by text or email describing the work and how it will be priced, then follow up with a formal change order.

What to include in a change order

  • Project name, address and original contract date.
  • Change order number.
  • Description of the change.
  • Reason for the change: client request, unforeseen condition or code requirement.
  • Price change: added cost or credit.
  • Updated contract total.
  • Schedule change, if any.
  • Payment terms for the change.
  • Signatures and dates from you and the client.

Keep change orders numbered and filed with the project records.

How to price a change order

Include every cost

  • Labor, including time to plan, order and coordinate.
  • Materials, with your usual markup.
  • Equipment, if needed.
  • Subcontractor costs, plus your coordination.
  • Permit revisions or additional inspections.
  • Overhead and profit.
  • Schedule impact, such as extra days on site.
  • Rework, if completed work has to be removed or redone.
  • Restocking fees for returned materials.

Example: adding recessed lights

These numbers are illustrative.

A client asks an electrician to add four recessed lights to a job already in progress.

ItemCalculationAmount
Labor5 hours × $121 (rate including overhead and profit)$605
Materials$240 + 25% markup$300
Permit revision and administration—$75
Change order total$980

Without a change order, many contractors would have charged only for the fixtures or nothing at all, losing nearly $1,000 on one “small” request.

Costs contractors often forget

  • Time spent on the change order itself: measuring, pricing, ordering.
  • Extra trips to the supply house.
  • Delays to other jobs caused by staying longer.
  • Coordination with other trades.

Deductive change orders: when work is removed

Sometimes a client removes work from the scope. The credit shouldn’t automatically equal the original price of that work, because you may have already incurred costs.

Example

These numbers are illustrative.

  • Original price of the removed item: $1,000
  • Materials already purchased: $300, returnable with a 20% restocking fee of $60
  • Planning and ordering time already spent: 1 hour × $121

Credit to the client: $1,000 − $60 − $121 = $819

Explain the calculation clearly so the client understands why the credit is less than the original line item.

When clients say “just do it, we’ll sort it out later”

This is how most change order disputes start. Respond politely but firmly:

  • “Happy to do it. I’ll send you a quick change order with the price so we’re both on the same page.”
  • Send a short written change order immediately, by email or through your software.
  • Wait for approval before starting.

Most clients appreciate clarity. Those who resist written approval are the ones most likely to dispute the charge later.

Getting paid for change orders

  • Small changes: bill with the next progress payment or final invoice, as agreed.
  • Larger changes: consider requiring a payment or deposit before the work starts, especially if materials must be ordered.
  • Track change orders separately on invoices so clients can see what was added.

Unpaid change orders are a common reason for slow final payments. Clear documentation makes collection easier.

Handling disputes

If a client disputes a change order:

  1. Refer to the signed document and your contract’s change order clause.
  2. Show your records: photos, messages, timesheets and receipts.
  3. Stay calm and factual.
  4. Consider compromise on small amounts if it preserves the relationship.
  5. Know your legal options, such as mechanics’ lien rights, which vary by state and have strict deadlines.

The best defense is a written, signed change order before the work.

Tools that help

  • Change order templates in your estimating or field service software.
  • Electronic signatures so clients can approve from their phone.
  • Photos of conditions before and after the change.
  • Job costing to track how changes affect profit.

Common mistakes

  • Doing work on verbal approval.
  • Pricing only materials.
  • Forgetting schedule impact.
  • Giving full credit for removed work after costs were incurred.
  • Billing change orders months later.
  • No change order clause in the contract.

Frequently asked questions

What is a change order in construction?
A written agreement that changes the scope, price or schedule of a contract, signed by the contractor and the client.

Should change orders be signed before the work starts?
Yes, whenever possible. Signed approval before work is the best protection against disputes.

How do I price a change order?
Include labor, materials with markup, equipment, permits, overhead, profit and schedule impact, plus time spent planning the change.

What if a client refuses to sign a change order?
Explain that changes require written approval under the contract. If they still refuse, don’t do the extra work.

How do I handle unforeseen conditions?
Document them with photos, explain them to the client, price the additional work in a change order and get approval before continuing.