This calculator is for planning and review only. Results depend on the numbers you enter.
Every estimate is a prediction. Job costing tells you whether the prediction was right. Without it, you only know whether the business made money at the end of the year, not which jobs made money, which ones didn’t and why.
This calculator compares what you estimated with what a job actually cost, category by category: labor, materials, equipment, subcontractors, permits and overhead. It shows your estimated and actual profit margin, the difference in dollars and the biggest source of overruns, so you can fix your next estimate.
Quick answer: job costing means tracking the actual labor hours, materials and other costs of each job and comparing them with your estimate. Add overhead using your overhead rate, subtract total cost from revenue (including approved change orders) and compare actual profit with estimated profit. The biggest differences show where your estimates need to improve.
Job costing calculator
Enter what you estimated and what the job actually cost. See where the money went and what you really made.
| Item | Estimate | Actual |
|---|---|---|
| Contract priceWhat the client agreed to pay | $ |
Same as estimate |
| Approved change ordersExtra revenue added during the job | — | $ |
| Labor hours | hrs |
hrs |
| Burdened labor rateWage plus payroll taxes, workers’ comp, benefits | $ |
Same as estimate |
| Materials | $ |
$ |
| Equipment rental | $ |
$ |
| Subcontractors | $ |
$ |
| Permits, disposal and other | $ |
$ |
| Overhead rate per labor hourFrom your overhead calculation | $ |
Same as estimate |
Estimated profit margin
0%
Actual profit margin
0%
Where the money went
| Cost | Estimate | Actual | Difference |
|---|
For planning and review only. Nothing you type is saved or sent anywhere.
How to use the calculator
Estimate column
Enter the numbers from your original estimate:
- Contract price: what the client agreed to pay.
- Labor hours you estimated.
- Burdened labor rate: wage plus payroll taxes, workers' comp and benefits. The same rate applies to estimated and actual hours.
- Materials, equipment rental, subcontractors and permits.
- Overhead rate per labor hour: from your overhead calculation. Overhead is applied to both estimated and actual hours.
Actual column
Enter what really happened:
- Approved change orders: extra revenue from signed changes.
- Actual labor hours, from timesheets.
- Actual materials, from invoices and receipts, net of returns.
- Actual equipment, subcontractor and other costs.
What the results mean
- Estimated profit margin: estimated profit ÷ contract price.
- Actual profit margin: actual profit ÷ (contract price + change orders).
- Where the money went: each cost category, estimate vs. actual, with the difference. Red means you spent more than estimated; green means less.
- Summary: how much more or less you made than planned, the biggest overrun and how many extra hours the crew worked.
The two bars show how revenue split between costs and profit in the estimate and in reality.
Example
We use the same sample job across our calculators, so you can follow it from pricing to job costing.
These numbers are illustrative.
| Item | Estimate | Actual |
|---|---|---|
| Contract price | $7,919 | $7,919 |
| Labor hours | 40 | 46 |
| Burdened labor rate | $45.50 | $45.50 |
| Materials | $2,640 | $2,810 |
| Equipment rental | $300 | $300 |
| Permits, disposal and other | $450 | $450 |
| Overhead rate per hour | $30 | $30 |
Results:
| Cost | Estimate | Actual | Difference |
|---|---|---|---|
| Labor | $1,820 | $2,093 | +$273 |
| Materials | $2,640 | $2,810 | +$170 |
| Equipment | $300 | $300 | $0 |
| Permits and other | $450 | $450 | $0 |
| Overhead | $1,200 | $1,380 | +$180 |
| Total cost | $6,410 | $7,033 | +$623 |
| Profit | $1,509 | $886 | −$623 |
- Estimated margin: 19.1%
- Actual margin: 11.2%
Six extra labor hours cost $273 in labor and added $180 in overhead, because overhead is applied per hour. Materials ran $170 over. Together, the job made $623 less than planned. Still profitable, but well below target.
Why extra hours cost more than you think
When a job takes longer, you don't just pay more labor. The job also absorbs more overhead: the truck, insurance and other costs that keep running while the crew is on site. In the example, each extra hour cost $45.50 in labor plus $30 in overhead, or $75.50 total.
That's why accurate hour estimates matter so much, and why reducing wasted time on site improves profit quickly.
Common reasons jobs go over budget
- Underestimated hours, especially for setup, cleanup and travel.
- Unforeseen conditions that weren't priced or turned into change orders.
- Scope changes done without change orders.
- Material waste, wrong orders and extra trips to the supply house.
- Price increases between estimate and purchase.
- Rework and callbacks.
- Crew inefficiency, waiting on materials or inspections.
How to track job costs
- Give every job a name or number and use it on timesheets, receipts and purchase orders.
- Track labor hours by job, using timesheets or field service software.
- Keep every receipt and invoice with the job number.
- Record returns so materials costs are accurate.
- Document change orders and add them to revenue.
- Review each job within a week of finishing, while details are fresh.
The concept is widely used across industries; this explanation of job costing covers the basics.
Turning job costing into better estimates
After a few jobs, patterns appear:
- Consistently over on labor? Increase your hour estimates for that job type, or look for productivity problems.
- Over on materials? Increase your waste factor or check ordering.
- Margins vary by job type? Focus marketing on the most profitable work.
- Certain clients cause overruns? Price them differently or tighten your scope and change order process.
Keep a simple record of estimated vs. actual hours for each common job type. Over time, it becomes your most valuable estimating tool.
Job costing for flat-rate pricing
If you use flat rates, job costing shows whether your pricebook is right. Compare actual hours and materials for each flat-rate task with the assumptions behind the price. If most jobs run over, the flat rate is too low.
Common mistakes
- Not tracking hours by job.
- Leaving overhead out of the job cost.
- Ignoring change orders in revenue.
- Forgetting returns and credits on materials.
- Reviewing jobs months later, when details are forgotten.
- Not using the results to adjust future estimates.
Frequently asked questions
What is job costing?
Tracking the actual costs of each job, including labor, materials, equipment, subcontractors, permits and overhead, and comparing them with the estimate.
Why should contractors use job costing?
It shows which jobs make money, where estimates are off and how to price future work more accurately.
Should overhead be included in job costing?
Yes. Without overhead, jobs look more profitable than they are. Apply overhead using your overhead rate.
How do change orders affect job costing?
Approved change orders add revenue. The costs of the extra work should be included in actual costs.
Does this calculator save my numbers?
No. It runs in your browser and doesn't save or send anything you enter.